The challenge
The customer was launching a retrofit module for an existing vehicle platform. Volumes were uncertain — somewhere between 40,000 and 120,000 units a month — and the launch date could not move because it was tied to a homologation window.
Their previous supplier had quoted a 22-week tooling lead time. With packaging, PPAP and shipping added, the launch would have slipped a full quarter. They needed parts earlier, without committing to a full production mould before the design was frozen.
What we did
- Reviewed the housing design in four days and flagged two ribs that would have caused sink marks on the A-surface.
- Built an aluminium bridge tool for 60,000 units so validation could start while production tooling was cut.
- Ran PPAP level 3 documentation, including CMM dimensional reports and material certificates.
- Set up a kanban agreement: two weeks of consignment stock at the customer's plant, replenished on a weekly schedule call.
“The bridge tool was the decision that saved the launch. We validated on real moulded parts in week six, not week twenty-two.”
Results
Serial production started in week 19 and ran for twelve months without a line stop caused by the housing. Scrap stayed under 0.6% across the run, with the second cavity added in month four once the design freeze cleared.
Following the first year, the customer extended the programme to include two additional brackets and moved inspection responsibility to Irongrid, removing a warehouse step from their own flow.