Home About Us Services Projects Blog Reviews
Company
CNC machining Case study Privacy Policy Terms & Conditions Request a Quote
Home / Projects / 1.2M units
Case study · Automotive

1.2M units delivered across 12 months, zero line stops recorded.

Two moulded housings, one bridge tool and a kanban agreement that moved a European Tier-1 supplier from monthly panic to a predictable build schedule.

SectorAutomotive
Year2025
Volume1.2M units / yr
ProcessesMoulding · Assembly
On-time99.4%
Moulded housings on the production conveyor Injection cell 4 · housing run

The challenge

The customer was launching a retrofit module for an existing vehicle platform. Volumes were uncertain — somewhere between 40,000 and 120,000 units a month — and the launch date could not move because it was tied to a homologation window.

Their previous supplier had quoted a 22-week tooling lead time. With packaging, PPAP and shipping added, the launch would have slipped a full quarter. They needed parts earlier, without committing to a full production mould before the design was frozen.

What we did

  • Reviewed the housing design in four days and flagged two ribs that would have caused sink marks on the A-surface.
  • Built an aluminium bridge tool for 60,000 units so validation could start while production tooling was cut.
  • Ran PPAP level 3 documentation, including CMM dimensional reports and material certificates.
  • Set up a kanban agreement: two weeks of consignment stock at the customer's plant, replenished on a weekly schedule call.
“The bridge tool was the decision that saved the launch. We validated on real moulded parts in week six, not week twenty-two.”

Results

Serial production started in week 19 and ran for twelve months without a line stop caused by the housing. Scrap stayed under 0.6% across the run, with the second cavity added in month four once the design freeze cleared.

Following the first year, the customer extended the programme to include two additional brackets and moved inspection responsibility to Irongrid, removing a warehouse step from their own flow.

Inspector measuring a moulded housing
Press-side inspection using the control plan agreed at PPAP.
Outcome

0 line stops

Twelve months of serial production with no customer line interruption.

Outcome

99.4% on-time

Weekly schedule calls and two weeks of consignment stock.

Outcome

6 weeks to validation

Bridge tooling let the customer test real moulded parts early.

Ready when you are

Send drawings today, get a quote in 24 hours.

Upload CAD files, share volumes and tolerances, and our engineering team returns a DFM-reviewed quote with tooling costs and lead time.